101608-6010 ZEXEL 9 400 611 999 BOSCH INJECTION-PUMP ASSEMBLY 9400611999 1016086010 me170453


101608-6010 INJECTION-PUMP ASSEMBLY
Rating:
20
Buy INJECTION-PUMP ASSEMBLY 101608-6010 zexel genuine, new aftermarket engine parts with delivery

Information injection-pump assembly

BOSCH 9 400 611 999 9400611999
ZEXEL 101608-6010 1016086010
MITSUBISHI ME170453 me170453

Service parts 101608-6010 INJECTION-PUMP ASSEMBLY:

1. _
2. FUEL INJECTION PUMP 101060-9700
3. GOVERNOR 105932-2990
4. SUPPLY PUMP 105210-4641
5. AUTOM. ADVANCE MECHANIS 105643-0160
6. COUPLING PLATE
7. COUPLING PLATE
8. _
9. _
10. NOZZLE AND HOLDER ASSY 105100-6030
11. Nozzle and Holder ME035655
12. Open Pre:MPa(Kqf/cm2) 21.6{220}
13. NOZZLE-HOLDER 105031-3900
14. NOZZLE 105015-5700
15. NOZZLE SET

Include in #1:

101608-6010 as INJECTION-PUMP ASSEMBLY

Include in #2:

Cross reference number

BOSCH 9 400 611 999 9400611999
ZEXEL 101608-6010 1016086010
MITSUBISHI ME170453 me170453


Zexel num
Bosch num
Firm num
Name
101608-6010 
101608-6011 
9 400 611 999 
ME170453  MITSUBISHI
INJECTION-PUMP ASSEMBLY
6D14 * K 14BE PE6A PE

Calibration Data:

Adjustment conditions
Test oil
1404 Test oil
  ISO4113 or {SAEJ967d}
Test oil temperature degC   40 40 45
Nozzle and nozzle holder   105780-8140
Bosch type code   EF8511/9A
Nozzle   105780-0000
Bosch type code   DN12SD12T
Nozzle holder   105780-2080
Bosch type code   EF8511/9
Opening pressure MPa   17.2
Opening pressure kgf/cm2   175
Injection pipe
Outer diameter - inner diameter - length (mm)
mm   6-2-600
Overflow valve   131424-5520
Overflow valve opening pressure kPa   255 221 289
Overflow valve opening pressure kgf/cm2   2.6 2.25 2.95
Tester oil delivery pressure kPa   157 157 157
Tester oil delivery pressure kgf/cm2   1.6 1.6 1.6
Direction of rotation (viewed from drive side)
Left
  L
Injection timing adjustment
Direction of rotation (viewed from drive side)
Left
  L
Injection order   1-5-3-6- 2-4
Pre-stroke mm   3.3 3.25 3.35
Beginning of injection position
Governor side
  NO.1
Difference between angles 1
Cal 1-5
deg.   60 59.5 60.5
Difference between angles 2
Cal 1-3
deg.   120 119.5 120.5
Difference between angles 3
Cal 1-6
deg.   180 179.5 180.5
Difference between angles 4
Cyl.1-2
deg.   240 239.5 240.5
Difference between angles 5
Cal 1-4
deg.   300 299.5 300.5
Injection quantity adjustment
Adjusting point   -
Rack position   11
Pump speed r/min   850 850 850
Each cylinder's injection qty mm3/st.   65 63 67
Basic   *
Fixing the rack   *
Standard for adjustment of the maximum variation between cylinders   *
Injection quantity adjustment_02
Adjusting point   H
Rack position   9.5+-0.5
Pump speed r/min   275 275 275
Each cylinder's injection qty mm3/st.   10.5 9 12
Fixing the rack   *
Standard for adjustment of the maximum variation between cylinders   *
Injection quantity adjustment_03
Adjusting point   A
Rack position   R1(11)
Pump speed r/min   850 850 850
Average injection quantity mm3/st.   65 64 66
Basic   *
Fixing the lever   *
Injection quantity adjustment_04
Adjusting point   B
Rack position   R1(11)
Pump speed r/min   1450 1450 1450
Average injection quantity mm3/st.   77.5 75.5 79.5
Fixing the lever   *
Injection quantity adjustment_05
Adjusting point   C
Rack position   R1+0.4
Pump speed r/min   600 600 600
Average injection quantity mm3/st.   59.7 55.7 63.7
Fixing the lever   *
Injection quantity adjustment_06
Adjusting point   I
Rack position   -
Pump speed r/min   100 100 100
Average injection quantity mm3/st.   90 70 110
Fixing the lever   *
Rack limit   *
Timer adjustment
Pump speed r/min   900--
Advance angle deg.   0 0 0
Remarks
Start
 
Timer adjustment_02
Pump speed r/min   850
Advance angle deg.   0.5
Timer adjustment_03
Pump speed r/min   900
Advance angle deg.   0.8
Timer adjustment_04
Pump speed r/min   1200
Advance angle deg.   2.6 2.1 3.1
Timer adjustment_05
Pump speed r/min   1500
Advance angle deg.   5.5 5 6
Remarks
Finish
 

Test data Ex:

Governor adjustment

Test data 101608-6010
N:Pump speed R:Rack position (mm) (1)Torque cam stamping: T1 (2)Tolerance for racks not indicated: +-0.05mm. (3)RACK LIMIT
----------
T1=D52
----------

Speed control lever angle

Test data 101608-6010
F:Full speed I:Idle (1)Use the hole at R = aa (2)Stopper bolt setting
----------
aa=40mm
----------
a=18.5deg+-5deg b=40.5deg+-3deg

Stop lever angle

Test data 101608-6010
N:Pump normal S:Stop the pump. (1)Set the stopper bolt at speed = aa and rack position = bb. Confirm non-injection. (2)After setting the stopper bolt, confirm non-injection at speed = cc and rack position = dd. (3)Rack position = approximately ee (speed lever full, speed = ff). (4)Free (at delivery) (5)Normal use set at engine manufacturer.
----------
aa=1450r/min bb=4.7-0.5mm cc=275r/min dd=(6.7)mm ee=15mm ff=0r/min
----------
a=38.5deg+-5deg b=(29deg) c=17deg+-5deg

0000001501 LEVER

Test data 101608-6010
(A) Idle (B) Full speed (C) Base lever (D) Accelerator lever (E) Accelerator lever delivery position 1. Measure speed lever angle (1)Measure the angle when the accelerator lever (D) contacted the base lever (C) at a.
----------

----------
b=40.5deg+-3deg c=18.5deg+-5deg

0000001601 ACS

Test data 101608-6010
(A) Housing (B) Snap ring (C) adjusting screw (D) Set screw (E): Push rod (F) Spacer 1. Adjustment of the aneroid compensator (1)Adjust with the (D) set screw so that the clearance between the (A) housing and (B) snap ring is L1. (2)Select the push rod (E) so that the distance from the end surface of the (F) spacer becomes L2. (3)(C) Turn the screw to adjust the beginning of aneroid compensator operation. 2. Adjustment when mounting the governor. (1)Set the speed of the pump to N1 r/min and fix the control lever at the full set position. (2)Adjust using screw C to obtain the performance shown in the graph above. (3)After final adjustment, confirm that the gap between housing (A) and snapring (B) is L3.
----------
N1=850r/min L1=1.4~1.7mm L2=0.5+-0.5mm L3=0.1~0.5mm
----------
Ra=R1(11)mm Rb=R1-0.3mm Pa=89.8+-2.7kPa(674+-20mmHg) Pb=79.4kPa(596mmHg) Q1=65+-1cm3/1000st Q2=(59)cm3/1000st

Timing setting

Test data 101608-6010
(1)Pump vertical direction (2)Position of timer's tooth at No 1 cylinder's beginning of injection (3)B.T.D.C.: aa (4)-
----------
aa=16deg
----------
a=(1deg)




Have questions with 101608-6010?





Group cross 101608-6010 ZEXEL

Mitsubishi 

9 400 611 331 
ME170452 
INJECTION-PUMP ASSEMBLY
6D16T7
F 01G 09U 1JW 
ME306179 
INJECTION-PUMP ASSEMBLY
6D16T7
101608-6010  

101608-6011 
9 400 611 999 
ME170453 
INJECTION-PUMP ASSEMBLY
6D14
F 019 Z20 010 
ME302680 
INJECTION-PUMP ASSEMBLY
6D14
9 400 615 833 
ME170454 
INJECTION-PUMP ASSEMBLY
6D14
9 400 615 834 
ME170455 
INJECTION-PUMP ASSEMBLY
6D16
F 019 Z20 011 
ME302675 
INJECTION-PUMP ASSEMBLY
6D16
 
 
INJECTION-PUMP ASSEMBLY

Mitsubishi 

9 400 615 835 
ME170456 
INJECTION-PUMP ASSEMBLY
6D16
9 400 619 939 
ME302676 
INJECTION-PUMP ASSEMBLY
6D16
 
 
INJECTION-PUMP ASSEMBLY

Mitsubishi 

9 400 611 755 
ME170457 
INJECTION-PUMP ASSEMBLY
6D16
9 400 611 605 
ME170458 
INJECTION-PUMP ASSEMBLY
6D16
9 400 619 711 
ME302677 
INJECTION-PUMP ASSEMBLY
6D16
9 400 615 836 
ME170459 
INJECTION-PUMP ASSEMBLY
6D16
9 400 611 194 
ME170460 
INJECTION-PUMP ASSEMBLY
6D16T
F 019 Z20 012 
ME302674 
INJECTION-PUMP ASSEMBLY
6D16T
 
 
INJECTION-PUMP ASSEMBLY

Mitsubishi 

9 400 611 520 
ME170461 
INJECTION-PUMP ASSEMBLY
6D16T2
Back to top